P’Harcourt Refinery Kick-Off Postponed Again

The Port Harcourt Refining Company has again failed to commence operations after about six postponements.

The refinery is under the management of the Nigerian National Petroleum Company Limited in Rivers State,

According to the Punch,
promises made to Nigerians by the Federal Ministry of Petroleum Resources and NNPC about the refinery have continued to witness multiple failures.

Since December 2023, NNPC, which is in charge of all the government refineries, has given Nigerians different dates, assuring citizens that the refinery would begin the sale of refined products soon.

In July, the Group Chief Executive Officer of the NNPC, Mele Kyari, stated categorically that the refinery would come into operation in early August.

The same Kyari said in 2019 that the NNPC would deliver all the country’s four refineries before the end of former President Muhammadu Buhari’s administration.

While appearing before the senate recently in July, Kyari boasted, “I can confirm to you, Mr Chairman, that by the end of the year, this country will be a net exporter of petroleum products.

“Specific to NNPC refineries, we have spoken to a number of your committees, and it is impossible to have the Kaduna refinery come into operation before December, it will get to December, both Warri and Kaduna, but that of Port Harcourt will commence production early August this year.”

However, as August nears midpoint, the refinery has yet to commence operations, creating concerns that this might be another failed promise from NNPC.

Replying to inquiries from our correspondent on Tuesday, the NNPC said it was on course, even when the early August promise has expired.

READ ALSO

Dangote Refinery: Why We Reduce Stake NNPC

Man Kills Son For Misplacing Sewing Thread

In a chat with our correspondent, the NNPC spokesperson, Olufemi Soneye, tersely replied, “We are on course.”

Soneye did not reply to further questions, asking if he meant the refinery would still operate this month.

It would be recalled that the 210,000 barrels per day refinery was said to have reached what the NNPC called mechanical completion of rehabilitation work in December.

It stated that the facility would start refining 60,000 barrels of crude oil daily after last year’s Christmas break.

Later in January, Kyari said the refinery was being tested and would be ready by the end of January.

During the second month of the year, the Shell Petroleum Development Company of Nigeria Limited completed the supply of 475,000 barrels of crude oil to the Port Harcourt refinery, raising the expectations of marketers that production was set to commence.

This came a few weeks after NNPC said in January it was seeking to engage reputable and credible operations and maintenance companies to run the Port Harcourt refinery. NNPC did not disclose whether or not it had secured bidders to run the refinery.

In mid-March, Kyari said the Port Harcourt refinery would commence operations in two weeks, April.

“We are serving this country with honour and dignity. And we will make sure that the promises we make on the rehabilitation of these refineries will take place,” Kyari stated after he appeared before the Senate Ad-hoc Committee investigating the various turnaround maintenance projects of the country’s refineries.

As the April deadline elapsed, independent petroleum marketers told The PUNCH that the facility would begin production by the end of July.

Commenting on this, NNPC’s Chief Corporate Communications Officer, Soneye, said regulatory approvals from international bodies were the only impediment stalling the operational commencement of the refinery.

“We have said that the mechanical completion has been done and every other thing is done. There is crude oil and all the pipes are working; we are only waiting for regulatory approvals. As I said, some of our materials and the things we use have to do with nuclear, and we need the nuclear authorities to give us approval to use all those things at the site.

“And some of these approvals come from bodies outside of Nigeria. Until they give us those approvals, we can’t begin operations. We are ready to go but if something happens without it, which would be another issue. Everything has been completed in terms of our work, and once we get those approvals, it will start operations,” Soneye revealed in May.

 

Punch

Kazeem Badmus

Kazeem Badmus is a graduate of Mass Communication with years of experience. A professional in journalism and media writing, Kazeem prioritses accuracy and factual reportage of issues. He is also a dexterous finder of the truth with conscious delivery of unbiased and development oriented stories.

Recent Posts

Judge’s Absence Stalls Ruling In Binance Executive’s Bail Plea

The absence of Justice Emeka Nwite of the Abuja Division of the Federal High Court…

2 hours ago

Ondo Gov Sacks Aide Over Alleged Bribery

The Governor of Ondo State, Lucky Aiyedatiwa, has sacked the Special Assistant on Forestry for…

2 hours ago

Women Affairs Ministry Pledges Support For Dismissed Army Officer

The Federal Ministry of Women Affairs has vowed to enhance the reintegration process of Ruth…

2 hours ago

Court Sacks House Of Reps Member

The Court of Appeal in Enugu State has upheld the ruling of an election tribunal…

2 hours ago

You Lack Power To Suspend LG Chair – Groups Berate Lagos Assembly

●Protest Illegal Suspension Of Alimosho LG Chairman Human rights groups on Tuesday protested at the…

3 hours ago

Army General Detained For Allegedly Stealing Palliative Rice

A Nigerian military commander, identified Brigadier General M.A. Sadiq of 3 Brigade Kano State has…

3 hours ago

This website uses cookies.